The() defines the phases that connect the beginning of a project to its end.
A.schedule
B.project life cycle
C.temporary
D.milestone
您可能感興趣的試卷
你可能感興趣的試題
()means that every project has a definite beginning and a definite end.
A.Project phase
B.Unique
C.Temporary
D.Closure
() is one of the quality planning outputs.
A.Scope base line
B.Cost of quality
C.Product specification
D.Quality checklist
The inputs of developing project management plan do not include()
A.project charter
B.stakeholder management strategy
C.project scope statement
D.outputs from planning processes
Which of the following statement related to PMO is not correct?()
A.The specific form, function, and structure of a PMO are dependent upon the needs of the organization that it supports.
B.One of the key features of a PMO is managing shared resources across all projects administered by the PMO.
C.The PMO focuses on the specified project objectives.
D.The PMO optimizes the use of shared organizational resources across all projects.
最新試題
()involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance. These other projects can be within the performing organization or outside of it, and can be within the same or in another application area.
空白(2)處應(yīng)選擇()
Which of the following statement related to PMO is not correct?()
PDM includes four types of dependencies or precedence relationships: (). The completion of the successor activity depends upon the initiation of the predecessor activity.
()is a category assigned to products or services having the same functional use but different technical characteristics. It is not same as quality.
The()provides the project manager with the authority to apply organizational resources to project activities.
In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including() .
空白(1)處應(yīng)選擇()
The inputs of developing project management plan do not include()
() is one of the quality planning outputs.