()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.
A.Plannedvalue
B.Earned value
C.Actualcost
D.Costvariance
您可能感興趣的試卷
- 2009年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
- 2009年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項(xiàng)目管理師下半年上午試卷
- 2010年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
- 2010年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項(xiàng)目管理師下半年上午試卷
- 2011年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
- 2011年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項(xiàng)目管理師下半年上午試卷
- 2012年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
你可能感興趣的試題
PDM includes four types of dependencies or precedence relationships:().The completion ofthe successor activity depends upon the initiation of the predecessor activity.
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.
A.estimating
B.defining
C.planning
D.sequencing
A.project scope statement
B.project requirement
C.project charter
D.product specification
The()provides the project manager with the authority to apply organizational resources to project activities.
A.project management plan
B.contract
C.project human resource plan
D.projectcharter
The()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.
A.Planning
B.Executing
C.Monitoring and Controlling
D.Closing
![](https://static.ppkao.com/ppmg/img/appqrcode.png)
最新試題
In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project's communication. According to Metcalfe's Law, a project with 10 stakeholders has()potential communication channels.
空白(2)處填()
Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.
空白(2)處填()
空白(1)處填()
空白(3)處填()
空白(2)處填()
空白(3)處填()
空白(1)處填()
The parties to government procurement refer to the principal entities of all kinds that enjoy rights and undertake obligations in government procurement, including the procuring entities, the ()and the procuring agencies.